文章來源:安(an)徽省(sheng)國資委 發布時間:2021-07-27
自今年2月下旬引江(jiang)濟淮工(gong)程全線復(fu)工(gong)以來,工(gong)程各項施工(gong)進(jin)(jin)展順利。截至6月底,引江(jiang)濟淮工(gong)程本年度(du)完成(cheng)投資57億元,達(da)到年度(du)計劃進(jin)(jin)度(du)目標;累計完成(cheng)投資506億元,占工(gong)程安徽段(duan)總投資875億元的57.8%。樅陽(yang)渠首樞(shu)紐工(gong)程、合(he)銅黃高(gao)速特大(da)橋(qiao)、蜀山樞(shu)紐工(gong)程等一批控制性節點(dian)、難(nan)點(dian)工(gong)程取得了重要進(jin)(jin)展。
入梅(mei)以(yi)來(lai),安徽省出現持續性(xing)強降雨。引江(jiang)(jiang)濟(ji)(ji)淮(huai)工(gong)(gong)程(cheng)(cheng)建(jian)設沿線緊密結合雨情(qing)、水(shui)(shui)(shui)情(qing)和工(gong)(gong)情(qing),迅速啟(qi)動防汛應急響應,科學有序調(diao)(diao)度(du)工(gong)(gong)程(cheng)(cheng)新開(kai)河(he)(he)渠與部分施工(gong)(gong)基坑過(guo)(guo)流進水(shui)(shui)(shui),及(ji)時發揮引江(jiang)(jiang)濟(ji)(ji)淮(huai)“大通道”行(xing)洪作用。采取外水(shui)(shui)(shui)歸槽、河(he)(he)道過(guo)(guo)流、基坑充水(shui)(shui)(shui)、拆除(chu)圍堰等應急措(cuo)施,在保證工(gong)(gong)程(cheng)(cheng)安全(quan)的前提(ti)下,調(diao)(diao)度(du)澇水(shui)(shui)(shui)進入主河(he)(he)槽過(guo)(guo)流,合理調(diao)(diao)水(shui)(shui)(shui)、泄水(shui)(shui)(shui)、蓄(xu)水(shui)(shui)(shui),切實減輕工(gong)(gong)程(cheng)(cheng)周邊排澇壓力。工(gong)(gong)程(cheng)(cheng)新開(kai)河(he)(he)槽以(yi)及(ji)部分基坑有效(xiao)蓄(xu)水(shui)(shui)(shui),切實提(ti)高了工(gong)(gong)程(cheng)(cheng)沿線防洪除(chu)澇能力。
【責任編輯:語謙】