文章來(lai)源:國家電(dian)網(wang)有限公司(si) 發(fa)布時間:2020-07-08
7月(yue)3日,西藏(zang)昌都供電公司組織參建單位開展同(tong)卡(ka)鎮110千伏輸變電工(gong)程首基鐵塔組立工(gong)作。這是今(jin)年西藏(zang)“三區三州”首個輸變電工(gong)程項目,投運后(hou),將(jiang)解決同(tong)卡(ka)鎮異地扶貧安置(zhi)點1120戶5599人用電問題。
同(tong)卡鎮110千伏輸變電工程(cheng)將(jiang)架設(she)線路59.5千米(mi),組立鐵(tie)塔155基,建設(she)1萬千伏安110千伏變電站一(yi)座(zuo)。
同卡鎮(zhen)110千伏(fu)輸變電工(gong)(gong)程施(shi)(shi)工(gong)(gong)區域平均海拔4450米,施(shi)(shi)工(gong)(gong)難度較大(da)。昌(chang)都供電公司要(yao)求(qiu),全面實施(shi)(shi)安(an)全風險(xian)精準(zhun)(zhun)管控,嚴(yan)格施(shi)(shi)工(gong)(gong)風險(xian)“一本(ben)賬”管理,確保(bao)(bao)安(an)全風險(xian)管控全覆蓋(gai)、無死(si)角;持續深化標(biao)(biao)準(zhun)(zhun)工(gong)(gong)藝應用,明(ming)確各層級責任(ren),嚴(yan)格執行標(biao)(biao)準(zhun)(zhun)工(gong)(gong)藝成(cheng)果體系,確保(bao)(bao)施(shi)(shi)工(gong)(gong)工(gong)(gong)序規范,保(bao)(bao)證施(shi)(shi)工(gong)(gong)質量,切實做到實施(shi)(shi)過(guo)程不變樣、實施(shi)(shi)效果不走(zou)樣;堅(jian)持綠(lv)(lv)色環保(bao)(bao)理念(nian),西藏高海拔生態系統脆弱,施(shi)(shi)工(gong)(gong)過(guo)程嚴(yan)格按照環保(bao)(bao)措(cuo)施(shi)(shi)方案作業,真(zhen)正做到綠(lv)(lv)色施(shi)(shi)工(gong)(gong)。
據(ju)介紹(shao),工程計劃2019年年底投運,投運后,可滿足同卡鎮異地(di)(di)扶(fu)(fu)貧安(an)置點用(yong)電(dian)需求,還能為當地(di)(di)精準扶(fu)(fu)貧提供電(dian)力保(bao)障。
【責任編輯:王莉】