文章來源:中國(guo)核工業(ye)集團有限(xian)公司 發布(bu)時間(jian):2021-08-11

8月(yue)8日,中核集團田灣核電(dian)5號(hao)機(ji)組(zu)首(shou)次并(bing)網(wang)成功(gong),各項技術指標均符合設計要求(qiu),標志著田灣核電(dian)5號(hao)機(ji)組(zu)正式(shi)進入(ru)并(bing)網(wang)調試階(jie)段,為后續機(ji)組(zu)投入(ru)商業運行奠定堅實基礎(chu)。
隨(sui)著田(tian)灣(wan)核(he)(he)(he)電(dian)(dian)(dian)(dian)5號機(ji)(ji)組首(shou)次并(bing)網(wang)(wang)成功,田(tian)灣(wan)核(he)(he)(he)電(dian)(dian)(dian)(dian)基地具備發電(dian)(dian)(dian)(dian)能力的(de)機(ji)(ji)組已達五臺,同時(shi)田(tian)灣(wan)核(he)(he)(he)電(dian)(dian)(dian)(dian)5號機(ji)(ji)組也(ye)成為中核(he)(he)(he)集團(tuan)乃至國內核(he)(he)(he)電(dian)(dian)(dian)(dian)建(jian)設(she)領域今(jin)年首(shou)臺實現并(bing)網(wang)(wang)發電(dian)(dian)(dian)(dian)的(de)核(he)(he)(he)電(dian)(dian)(dian)(dian)機(ji)(ji)組。
當日(ri)19時52分,隨著運行(xing)值(zhi)長(chang)發(fa)出并(bing)網指令(ling),田(tian)灣核(he)電(dian)5號機(ji)組主控(kong)室控(kong)制屏(ping)幕上“000”的負(fu)荷(he)顯示開始(shi)跳動,田(tian)灣核(he)電(dian)站5號機(ji)組正式(shi)進(jin)入(ru)帶負(fu)荷(he)試運行(xing)狀態(tai),并(bing)開始(shi)向(xiang)電(dian)網輸(shu)送電(dian)力(li)。
據(ju)了解,田(tian)灣核電(dian)5號機組(zu)于2015年12月27日(ri)正式開工建設(she)(she),經(jing)過(guo)4年多(duo)的建設(she)(she),歷(li)經(jing)土(tu)建、安(an)裝、調試(shi)、裝料(liao)、臨界等重大工程節點。此次并網后(hou),機組(zu)還將(jiang)進(jin)行多(duo)功率平臺的瞬態(tai)試(shi)驗(yan)和帶負荷試(shi)驗(yan)各項試(shi)驗(yan),待(dai)符合要(yao)求后(hou),將(jiang)進(jin)入滿功率示范(fan)運(yun)行考核。考核期(qi)間,機組(zu)的各項性能(neng)指標(biao)(biao)達到設(she)(she)計(ji)標(biao)(biao)準,機組(zu)狀態(tai)穩定,滿足電(dian)網相關要(yao)求,則表明機組(zu)具備正式商業(ye)運(yun)行條件(jian)。
【責(ze)任編輯:趙藝(yi)涵】