文章來源:中國(guo)華電集團(tuan)公司 發布時間:2011-02-03
1月28日,新疆華電喀什發電有(you)限責任公(gong)司二期2×50MW熱電聯產(chan)工程順利通(tong)過(guo)國家環保部環保驗(yan)收(shou)組的檢(jian)查(cha)驗(yan)收(shou)。
受國家環(huan)保(bao)部的(de)委托,由自治(zhi)區環(huan)保(bao)廳環(huan)評處(chu)副處(chu)長武新(xin)帶領的(de)環(huan)保(bao)驗(yan)(yan)收(shou)(shou)組(zu)(zu)一行(xing)(xing)7人,對華(hua)電喀(ka)什(shen)公司二(er)(er)期(qi)工(gong)(gong)程進行(xing)(xing)了(le)環(huan)保(bao)驗(yan)(yan)收(shou)(shou)現(xian)場(chang)檢(jian)查(cha)。驗(yan)(yan)收(shou)(shou)組(zu)(zu)在認真聽取了(le)該(gai)公司二(er)(er)期(qi)工(gong)(gong)程工(gong)(gong)作匯(hui)報,審閱、核實(shi)有關資料,實(shi)地檢(jian)查(cha)電除塵、脫硫裝(zhuang)置的(de)運行(xing)(xing)參數和運行(xing)(xing)管理等相關情況后,組(zu)(zu)織召開了(le)環(huan)保(bao)驗(yan)(yan)收(shou)(shou)現(xian)場(chang)會。驗(yan)(yan)收(shou)(shou)組(zu)(zu)認為(wei),該(gai)公司二(er)(er)期(qi)工(gong)(gong)程執行(xing)(xing)了(le)環(huan)保(bao)“三同時(shi)”制度,同步安裝(zhuang)了(le)電除塵、脫硫裝(zhuang)置等環(huan)保(bao)設施(shi),各項(xiang)環(huan)保(bao)設施(shi)運行(xing)(xing)穩定,參數滿(man)足(zu)環(huan)保(bao)要求。驗(yan)(yan)收(shou)(shou)組(zu)(zu)一致同意該(gai)公司二(er)(er)期(qi)工(gong)(gong)程通過環(huan)境(jing)保(bao)護驗(yan)(yan)收(shou)(shou)。