文章(zhang)來(lai)源:中國水利(li)水電(dian)建(jian)設集(ji)團公司 發布時(shi)間:2008-12-19
12月15日,由中國水電(dian)集團承建的柬埔(pu)寨甘(gan)再水電(dian)站右岸拌和及砂石系統建成投(tou)產,并(bing)順利生產第(di)一罐(guan)混凝土(tu)。
甘再水電站右岸拌(ban)和系統為國產(chan)HZ120-2S1500強制(zhi)式混(hun)凝土(tu)拌(ban)和站,拌(ban)和樓安裝有兩臺1.5立(li)(li)方(fang)米的混(hun)凝土(tu)攪拌(ban)機(ji),設計生(sheng)產(chan)能力為:每小時(shi)生(sheng)產(chan)常(chang)態混(hun)凝土(tu)120立(li)(li)方(fang)米,生(sheng)產(chan)碾(nian)壓混(hun)凝土(tu)90立(li)(li)方(fang)米。配(pei)套的人工(gong)砂石系統每小時(shi)生(sheng)產(chan)能力為100~150噸。
右岸拌和及(ji)砂石(shi)(shi)系(xi)統(tong)安裝(zhuang)任務于(yu)11月10日開(kai)始(shi)部(bu)署啟動,項(xiang)目(mu)(mu)經(jing)理白延(yan)慶在(zai)(zai)生產(chan)會上明(ming)確要求,系(xi)統(tong)必須于(yu)12月15日投(tou)(tou)(tou)產(chan),并作(zuo)為(wei)項(xiang)目(mu)(mu)部(bu)的(de)(de)(de)第(di)一個(ge)(ge)重點(dian)工(gong)(gong)(gong)期(qi)目(mu)(mu)標(biao)(biao)。當時系(xi)統(tong)基礎正在(zai)(zai)進行開(kai)挖,邊(bian)(bian)坡漿砌石(shi)(shi)擋墻(qiang)剛開(kai)始(shi)施(shi)工(gong)(gong)(gong),系(xi)統(tong)安裝(zhuang)需(xu)要的(de)(de)(de)四個(ge)(ge)平(ping)臺均未形成(cheng),系(xi)統(tong)設(she)(she)備在(zai)(zai)西港碼(ma)頭等(deng)待清關,材(cai)(cai)料(liao)都需(xu)要緊急采購。因(yin)此大(da)家都覺得12月15日投(tou)(tou)(tou)產(chan)的(de)(de)(de)目(mu)(mu)標(biao)(biao)太緊,幾乎(hu)沒信心(xin)完成(cheng)。在(zai)(zai)這(zhe)種情況下,項(xiang)目(mu)(mu)部(bu)及(ji)時調(diao)整生產(chan)計(ji)劃,將(jiang)優勢力(li)(li)量集中(zhong)到小系(xi)統(tong)建(jian)設(she)(she)上。由擔負(fu)左岸大(da)砂石(shi)(shi)系(xi)統(tong)建(jian)設(she)(she)的(de)(de)(de)水(shui)電八(ba)局(ju)砂石(shi)(shi)分局(ju)項(xiang)目(mu)(mu)部(bu)為(wei)主承擔右岸小拌和及(ji)砂石(shi)(shi)系(xi)統(tong)的(de)(de)(de)安裝(zhuang)任務,甘(gan)再項(xiang)目(mu)(mu)部(bu)負(fu)責土建(jian)施(shi)工(gong)(gong)(gong),設(she)(she)備、材(cai)(cai)料(liao)的(de)(de)(de)保障以及(ji)現(xian)場技(ji)術指導和服務。從11月11日起(qi),項(xiang)目(mu)(mu)部(bu)全體人(ren)(ren)員取(qu)消(xiao)星期(qi)天(tian)休息,前方施(shi)工(gong)(gong)(gong)人(ren)(ren)員起(qi)早摸黑的(de)(de)(de)干(gan),全力(li)(li)以赴投(tou)(tou)(tou)入到施(shi)工(gong)(gong)(gong)建(jian)設(she)(she)中(zhong)。一邊(bian)(bian)系(xi)統(tong)建(jian)設(she)(she)如(ru)火如(ru)荼,一邊(bian)(bian)導流明(ming)渠(qu)、壩肩、反調(diao)節堰開(kai)挖熱火朝天(tian),甘(gan)再工(gong)(gong)(gong)地掀起(qi)了第(di)一個(ge)(ge)施(shi)工(gong)(gong)(gong)高潮。
11月(yue)(yue)28日(ri),拌和(he)樓土建基礎完成,開始系統安裝(zhuang),至12月(yue)(yue)15日(ri),拌和(he)樓安裝(zhuang)完畢,系統經多次(ci)調試,聯動成功,具備生產混凝土條件(jian),歷(li)時18天。據(ju)在現場的拌和(he)樓廠家服務工程師說(shuo),這樣的系統由專業隊伍安裝(zhuang)一般要25天時間完成,這種速(su)度是非(fei)常之快的。
甘再項目右岸拌(ban)和(he)及(ji)砂石系(xi)統建成投產(chan),及(ji)時為導(dao)流(liu)明(ming)渠、施工道(dao)路(lu)等混(hun)凝土澆筑提(ti)供了條件,為2008年2月15日截流(liu)以(yi)及(ji)3月15日大壩開澆混(hun)凝土創造(zao)了有(you)利條件。