文章來源:國(guo)家電(dian)網(wang)公(gong)司 發布(bu)時間(jian):2009-07-31
7月25日20時57分,隨著倒(dao)送電試驗沖擊成功(gong),國內(nei)首(shou)條500千伏(fu)同塔雙回海上大跨(kua)越輸電線路(lu)工(gong)(gong)程(cheng)(cheng)——福(fu)建(jian)莆(pu)田燃氣電廠—莆(pu)田變電站(zhan)500千伏(fu)Ⅰ、Ⅱ回線路(lu)竣(jun)工(gong)(gong),其中Ⅱ回線路(lu)投運。據了(le)解(jie),7月28日22時登(deng)陸福(fu)清東瀚鎮的(de)臺(tai)風“鳳凰”給(gei)莆(pu)田帶(dai)來了(le)狂風暴雨,但該工(gong)(gong)程(cheng)(cheng)運行(xing)穩定,未(wei)受臺(tai)風影(ying)響。
該線路(lu)工(gong)程是(shi)國家(jia)重點工(gong)程莆(pu)田燃(ran)氣(qi)電(dian)(dian)廠的(de)(de)配套送出工(gong)程,也是(shi)福(fu)(fu)建(jian)(jian)(jian)電(dian)(dian)網接入新能源發電(dian)(dian)的(de)(de)里程碑工(gong)程。工(gong)程于2007年(nian)10月18日開工(gong),總投資3億多元,全長35.62千米(mi)(mi),建(jian)(jian)(jian)塔82基(ji),其(qi)中17號~21號段跨越莆(pu)田湄洲灣海域,跨越長度為3.114千米(mi)(mi)。該工(gong)程由福(fu)(fu)建(jian)(jian)(jian)省(sheng)電(dian)(dian)力設(she)計院自行設(she)計,福(fu)(fu)建(jian)(jian)(jian)省(sheng)第二電(dian)(dian)力建(jian)(jian)(jian)設(she)公司施工(gong)。工(gong)程投運(yun)后(hou)可有(you)效提高福(fu)(fu)建(jian)(jian)(jian)電(dian)(dian)網安全穩定(ding)運(yun)行水(shui)平,緩解迎峰度夏(xia)壓(ya)力。
據介(jie)紹,整個(ge)工程施工難度最大(da)的是跨(kua)海(hai)段,具(ju)有(you)鐵(tie)塔(ta)高、跨(kua)度寬(kuan)、基(ji)(ji)礎大(da)等特點,其中位于湄洲灣海(hai)域的直(zhi)線(xian)大(da)跨(kua)越塔(ta)19號塔(ta)是我國(guo)第(di)一(yi)基(ji)(ji)500千伏海(hai)上(shang)鐵(tie)塔(ta),塔(ta)高128.5米,重651.55噸。海(hai)中鐵(tie)塔(ta)基(ji)(ji)礎不(bu)僅(jin)要(yao)承(cheng)(cheng)受垂(chui)直(zhi)荷載,還要(yao)承(cheng)(cheng)受多(duo)方向較(jiao)大(da)水(shui)平荷載,樁(zhuang)(zhuang)基(ji)(ji)露出(chu)海(hai)平面較(jiao)多(duo),必須具(ju)有(you)較(jiao)大(da)的水(shui)平剛度。設(she)計人(ren)員反復(fu)比較(jiao)分析,最終采用了(le)鋼(gang)管樁(zhuang)(zhuang)基(ji)(ji)礎,這也是國(guo)內首次在500千伏線(xian)路建(jian)設(she)上(shang)采用此方案(an)。此外,設(she)計人(ren)員還取得(de)了(le)鋼(gang)管樁(zhuang)(zhuang)防(fang)腐、鐵(tie)塔(ta)基(ji)(ji)礎防(fang)風防(fang)浪、鐵(tie)塔(ta)基(ji)(ji)礎防(fang)撞(zhuang)等多(duo)個(ge)課題的研究(jiu)成果。
跨海(hai)(hai)段施工(gong)是對電力(li)(li)(li)基建施工(gong)實力(li)(li)(li)的大(da)考驗(yan)。在(zai)海(hai)(hai)面百米高(gao)空(kong)之上作(zuo)業,正常(chang)情況下風力(li)(li)(li)達6~7級(ji),天氣略有變(bian)化風力(li)(li)(li)就會(hui)超過7級(ji);海(hai)(hai)上作(zuo)業面窄(zhai),鋼管構件又長又重,運(yun)輸困難(nan),組立(li)技術要求高(gao),安(an)全控制更難(nan);再(zai)加上至(zhi)少需要15個月(yue)的工(gong)期(qi)被壓縮成9個月(yue),施工(gong)難(nan)度可(ke)想而知(zhi)。
針對工(gong)(gong)(gong)(gong)程特點,福建公司(si)大(da)膽(dan)采用(yong)新(xin)工(gong)(gong)(gong)(gong)藝、新(xin)技(ji)術、新(xin)裝(zhuang)備,提高施(shi)(shi)工(gong)(gong)(gong)(gong)質量(liang)和效(xiao)率(lv)。例如,海(hai)上鐵塔組立施(shi)(shi)工(gong)(gong)(gong)(gong)方案采用(yong)數字化(hua)立體動(dong)態模擬;地面工(gong)(gong)(gong)(gong)作(zuo)人(ren)員(yuan)使用(yong)高塔施(shi)(shi)工(gong)(gong)(gong)(gong)視頻(pin)監控系統,實時查(cha)看施(shi)(shi)工(gong)(gong)(gong)(gong)現場變化(hua)和人(ren)員(yuan)行為(wei),消除隱患。
施(shi)工(gong)單位(wei)強(qiang)化了高塔施(shi)工(gong)安全(quan)技術(shu)措(cuo)施(shi),在塔身內外(wai)設(she)置(zhi)安全(quan)網(wang),在垂直方(fang)向設(she)置(zhi)攀(pan)爬自鎖裝置(zhi),在水平(ping)方(fang)向上(shang)設(she)置(zhi)水平(ping)扶手,使用全(quan)方(fang)位(wei)的(de)防沖(chong)擊(ji)安全(quan)帶及速(su)差(cha)保護器,使高空作業人員處于全(quan)面保護中。針對福建多(duo)臺風的(de)氣候條(tiao)件,施(shi)工(gong)單位(wei)組(zu)織了海(hai)(hai)上(shang)安全(quan)應(ying)急預案演練,提高施(shi)工(gong)人員自防自救能力。福建公司還對參加跨海(hai)(hai)段施(shi)工(gong)的(de)技術(shu)骨干進行了封(feng)閉式軍訓,以(yi)提高協作能力和現(xian)場管(guan)理水平(ping)。
在9個月艱苦施工后,福(fu)建電力(li)鐵軍最終實現(xian)了“工期零拖延、安全零事故(gu)、質量零缺陷”的目標。