文章(zhang)來源:中國華電集(ji)團公司 發布時間(jian):2010-03-17
3月16日上午10時16分,中國華電集團公司寧夏靈武發電有限公司二期工程兩臺100萬千瓦超超臨界空冷機組施工現場,主廠房開始澆筑第一方混凝土,比計劃工期提前42天,標志著該公司二期工程主體施工正式展開。
該項目(mu)(mu)于(yu)2008年12月9日獲得國家(jia)(jia)發改委核(he)(he)準,被列入國家(jia)(jia)百萬(wan)千(qian)瓦機(ji)組空冷技術裝備(bei)自(zi)主(zhu)(zhu)(zhu)國產化示(shi)范項目(mu)(mu),是(shi)世界(jie)首臺(tai)百萬(wan)千(qian)瓦空冷機(ji)組項目(mu)(mu),也(ye)是(shi)國家(jia)(jia)重點開(kai)發區寧夏寧東煤電化基(ji)地開(kai)工(gong)(gong)(gong)(gong)建設(she)的“一(yi)號工(gong)(gong)(gong)(gong)程(cheng)”。工(gong)(gong)(gong)(gong)程(cheng)自(zi)2008年12月27日“破土”動(dong)工(gong)(gong)(gong)(gong)以來,該公司按(an)照“安、快、好、省、廉”的目(mu)(mu)標要求,充分發揮(hui)好業(ye)主(zhu)(zhu)(zhu)的工(gong)(gong)(gong)(gong)程(cheng)管理(li)主(zhu)(zhu)(zhu)導(dao)和(he)核(he)(he)心(xin)作用,全力(li)抓(zhua)好工(gong)(gong)(gong)(gong)程(cheng)建設(she)全過程(cheng)管理(li),著力(li)打(da)造世界(jie)空冷示(shi)范工(gong)(gong)(gong)(gong)程(cheng),爭創國家(jia)(jia)優質工(gong)(gong)(gong)(gong)程(cheng)金(jin)獎。他們克服(fu)冬(dong)季施工(gong)(gong)(gong)(gong)周期長、施工(gong)(gong)(gong)(gong)難度(du)大等許多困難,科(ke)學合(he)理(li)確定(ding)關鍵施工(gong)(gong)(gong)(gong)環節,有(you)效控制工(gong)(gong)(gong)(gong)程(cheng)進(jin)度(du)。加強過程(cheng)控制,統籌(chou)抓(zhua)好安全、質量(liang)、工(gong)(gong)(gong)(gong)期的關系。加強設(she)計(ji)(ji)協(xie)調,確保了施工(gong)(gong)(gong)(gong)圖紙及時到(dao)位。工(gong)(gong)(gong)(gong)程(cheng)節假日和(he)公休天連續(xu)施工(gong)(gong)(gong)(gong),使得破樁頭和(he)二次(ci)開(kai)挖工(gong)(gong)(gong)(gong)作提(ti)前完成(cheng)計(ji)(ji)劃,為順(shun)利澆筑(zhu)第(di)一(yi)方(fang)混凝土奠定(ding)了堅實基(ji)礎(chu)。