4月份以(yi)來,葛洲壩集團基(ji)礎公司(si)承擔的國內第三(san)大(da)水電工(gong)程——向家壩水電站上下(xia)(xia)游圍堰防滲墻(qiang)下(xia)(xia)帷幕灌漿進入大(da)規模施工(gong)沖刺階段。現(xian)場鉆機轟(hong)鳴,一派火熱施工(gong)景象。
按照生產計(ji)劃安(an)(an)排,4月25日(ri)前,向家壩水電(dian)站上下(xia)游圍堰防(fang)滲墻(qiang)(qiang)下(xia)帷(wei)幕灌漿必須(xu)全線(xian)完(wan)(wan)成(cheng),總灌漿量(liang)9800米(mi)。該項(xiang)目工(gong)(gong)程量(liang)大,工(gong)(gong)期緊,施(shi)工(gong)(gong)難度(du)大。為確保項(xiang)目如期完(wan)(wan)成(cheng),葛洲壩基礎公司向家壩項(xiang)目部加大資源配(pei)置(zhi)力(li)度(du),優化施(shi)工(gong)(gong)方案(an),開展勞動競賽,強化現(xian)場質量(liang)、安(an)(an)全、文明施(shi)工(gong)(gong)管理,推(tui)動工(gong)(gong)程建設快速進行(xing)。目前,葛洲壩人已完(wan)(wan)成(cheng)墻(qiang)(qiang)下(xia)帷(wei)幕灌漿6625米(mi),占工(gong)(gong)程總量(liang)的68%。4月25日(ri)前完(wan)(wan)成(cheng)全部灌漿任務,勝券在握。