文章來(lai)源:中國南方電網有限(xian)責(ze)任(ren)公司(si) 發布時間:2010-04-27
日前,小灣電站500千伏送出工程配套工程——500千伏和平至楚雄換流站線路工程順利投運,這是云南省第一次實施交流500千伏變電站和±800千伏換流站的對接,工程的建成投產對進一步強化云南電網500千伏主網架,同時為“云電送粵”奠定了堅實的基礎。
該配套工(gong)(gong)(gong)程(cheng)起于500千(qian)伏和平變(bian)電站,止于±800千(qian)伏楚雄換流站,線路全長27公(gong)里,于2008年(nian)10月開工(gong)(gong)(gong)建設,經過(guo)廣大參建人員的(de)努力,克服(fu)了(le)工(gong)(gong)(gong)期(qi)緊、任(ren)務重的(de)困難,按期(qi)投產。小灣電站500千(qian)伏送(song)出工(gong)(gong)(gong)程(cheng)是南方電網公(gong)司重點(dian)工(gong)(gong)(gong)程(cheng),同(tong)時(shi)也是云(yun)南省“雙(shuang)百”重點(dian)工(gong)(gong)(gong)程(cheng),是500千(qian)伏“云(yun)電送(song)粵”北通道工(gong)(gong)(gong)程(cheng)的(de)重要(yao)組成(cheng)部分。