兵器工業集團華錦公司“十一五”重點工程實現機械竣工

文章來源:中國兵器工業集團公司   發布時間:2010-06-11

  經(jing)過萬余(yu)名建設者22個(ge)月的艱苦奮戰,中國兵(bing)器(qi)工(gong)(gong)業集(ji)團華錦(jin)公司“十一五(wu)”重點工(gong)(gong)程建設全面完成(cheng)了打樁(zhuang)、基(ji)礎和地管(guan)、結構和設備安裝(zhuang)、工(gong)(gong)藝管(guan)線和電(dian)纜敷設和電(dian)氣設備安裝(zhuang)5個(ge)階段的全部(bu)施工(gong)(gong)任務,截(jie)止到5月31日(ri),多個(ge)項目(mu)陸續驗收,勝(sheng)利實現機械(xie)竣(jun)工(gong)(gong)。

  儲運工程實現全線機械竣工

  5月(yue)31日,該(gai)公司“十一五(wu)”重點工(gong)(gong)(gong)(gong)(gong)(gong)程(cheng)之(zhi)(zhi)(zhi)一的(de)儲運(yun)(yun)155公里輸油(you)管線順利通過(guo)竣(jun)(jun)工(gong)(gong)(gong)(gong)(gong)(gong)驗收(shou),至此,“十一五(wu)” 工(gong)(gong)(gong)(gong)(gong)(gong)程(cheng)的(de)關鍵項目(mu)——儲運(yun)(yun)工(gong)(gong)(gong)(gong)(gong)(gong)程(cheng)實現(xian)全(quan)線機(ji)械竣(jun)(jun)工(gong)(gong)(gong)(gong)(gong)(gong),這也(ye)是“十一五(wu)”工(gong)(gong)(gong)(gong)(gong)(gong)程(cheng)第一個整體竣(jun)(jun)工(gong)(gong)(gong)(gong)(gong)(gong)的(de)項目(mu)。自(zi)2008年3月(yue)1日儲運(yun)(yun)工(gong)(gong)(gong)(gong)(gong)(gong)程(cheng)開工(gong)(gong)(gong)(gong)(gong)(gong)建設(she)以(yi)來,按照“打(da)造兵器(qi)石(shi)化產業精品工(gong)(gong)(gong)(gong)(gong)(gong)程(cheng)”要求,堅持嚴(yan)(yan)之(zhi)(zhi)(zhi)又(you)嚴(yan)(yan)、細之(zhi)(zhi)(zhi)又(you)細、實之(zhi)(zhi)(zhi)又(you)實的(de)管理思(si)路(lu),多(duo)方協調化解矛盾(dun),嚴(yan)(yan)密推(tui)進施工(gong)(gong)(gong)(gong)(gong)(gong)進度,嚴(yan)(yan)肅(su)過(guo)程(cheng)質量控(kong)制(zhi),嚴(yan)(yan)格保證施工(gong)(gong)(gong)(gong)(gong)(gong)安全(quan)。克服時(shi)間緊、任務重、建設(she)環境復雜、管線穿越(yue)路(lu)河難度大等實際困難,高(gao)標準、高(gao)質量完成了工(gong)(gong)(gong)(gong)(gong)(gong)程(cheng)建設(she)任務,實現(xian)全(quan)線機(ji)械竣(jun)(jun)工(gong)(gong)(gong)(gong)(gong)(gong)。

  乙烯工程雙聚裝置順利通過驗收

  5月30日,該公司“十一五”重(zhong)點工(gong)(gong)(gong)程(cheng)(cheng)之(zhi)一的(de)(de)乙烯(xi)工(gong)(gong)(gong)程(cheng)(cheng)聚(ju)乙烯(xi)、聚(ju)丙烯(xi)兩大(da)主體裝置(zhi)雙(shuang)雙(shuang)通過(guo)總指揮部驗(yan)(yan)收,這(zhe)是乙烯(xi)工(gong)(gong)(gong)程(cheng)(cheng)率先(xian)通過(guo)驗(yan)(yan)收的(de)(de)主體裝置(zhi)。“雙(shuang)聚(ju)”項目于2008年(nian)2月14日正式開工(gong)(gong)(gong)建(jian)設(she)(she),在15個月的(de)(de)施(shi)(shi)(shi)(shi)工(gong)(gong)(gong)建(jian)設(she)(she)中(zhong),全體建(jian)設(she)(she)人(ren)員克(ke)服工(gong)(gong)(gong)期短(duan)、設(she)(she)備到貨晚、雨季施(shi)(shi)(shi)(shi)工(gong)(gong)(gong)、設(she)(she)計變更等多重(zhong)困難,精(jing)心(xin)組織,晝夜施(shi)(shi)(shi)(shi)工(gong)(gong)(gong),強力推進施(shi)(shi)(shi)(shi)工(gong)(gong)(gong)進度(du)。在搶抓施(shi)(shi)(shi)(shi)工(gong)(gong)(gong)進度(du)的(de)(de)同時,嚴控施(shi)(shi)(shi)(shi)工(gong)(gong)(gong)質量,狠抓安全施(shi)(shi)(shi)(shi)工(gong)(gong)(gong),特別是進入(ru)驗(yan)(yan)收階(jie)段,按照“三(san)查(cha)四定”要求,嚴查(cha)問題,深刻整改,確保了(le)工(gong)(gong)(gong)程(cheng)(cheng)的(de)(de)順利竣工(gong)(gong)(gong)驗(yan)(yan)收。

  乙烯總變電所勝利報捷

  5月27日,已投用三個多月的(de)該公(gong)司乙(yi)烯總變電(dian)(dian)(dian)所(suo)順利(li)通(tong)過機械(xie)竣工(gong)驗(yan)收。按照工(gong)程建設(she)“電(dian)(dian)(dian)氣(qi)先行(xing)”的(de)部(bu)署和(he)要求(qiu),他(ta)們(men)先后(hou)戰勝(sheng)了設(she)計滯后(hou)造(zao)成(cheng)工(gong)程被(bei)迫停工(gong)、大風雪影響(xiang)電(dian)(dian)(dian)纜敷設(she)等困難,搶(qiang)工(gong)期,抓(zhua)質量,在(zai)2009年1月12日具(ju)備受(shou)電(dian)(dian)(dian)條(tiao)件(jian)的(de)基礎(chu)上(shang),于2月25日實(shi)現7臺(tai)變壓(ya)器全部(bu)具(ju)備向乙(yi)烯各分變電(dian)(dian)(dian)所(suo)送電(dian)(dian)(dian)條(tiao)件(jian)。隨著100余(yu)項問題的(de)徹底(di)整改,乙(yi)烯總變電(dian)(dian)(dian)所(suo)全面(mian)通(tong)過竣工(gong)驗(yan)收。

  油化成品油罐區實現機械竣工

  5月29日(ri),該公司(si)油化(hua)成(cheng)(cheng)品油罐區順(shun)利通(tong)過竣工(gong)(gong)驗收,實現機械竣工(gong)(gong)。自2008年3月28日(ri)油化(hua)成(cheng)(cheng)品油罐區破(po)土動(dong)工(gong)(gong)以來,公司(si)克服時間緊、任務重、設(she)計變更以及(ji)材料到貨滯后(hou)等(deng)諸多不利因素,科(ke)學組織,頑強拼(pin)搏,在確保安(an)全(quan)和質量的前提下,力(li)搶工(gong)(gong)期,先后(hou)完成(cheng)(cheng)了“5.30”基礎(chu)施工(gong)(gong)和“9.30”罐體制作以及(ji)設(she)備(bei)及(ji)工(gong)(gong)藝管線(xian)安(an)裝(zhuang)、水壓試驗、單機試車等(deng)各階段節(jie)點(dian)目(mu)標。目(mu)前,油化(hua)成(cheng)(cheng)品油罐區已具備(bei)試生(sheng)產條件。

  乙烯水系統全線竣工并投入運行

  由該(gai)公司(si)乙烯給(gei)水(shui)(shui)(shui)及高壓(ya)消防水(shui)(shui)(shui)泵(beng)站(zhan)、乙烯雨(yu)水(shui)(shui)(shui)池、污(wu)水(shui)(shui)(shui)泵(beng)站(zhan)、第二熱水(shui)(shui)(shui)站(zhan)、脫鹽(yan)水(shui)(shui)(shui)站(zhan)、給(gei)水(shui)(shui)(shui)變電所和(he)乙烯第一、二循環水(shui)(shui)(shui)場等(deng)(deng)8個單體(ti)項目組成的(de)乙烯水(shui)(shui)(shui)系統實現全線告捷(jie),順利通(tong)過竣(jun)工(gong)(gong)驗收(shou)并已投入(ru)生產運行(xing)。其(qi)中(zhong),前(qian)6個單體(ti)項目被評(ping)為“十一五”精品工(gong)(gong)程(cheng)。施(shi)工(gong)(gong)中(zhong),他(ta)們克服建筑結構復雜(za)、作業(ye)面分散、材料(liao)到貨滯后、交叉(cha)作業(ye)多等(deng)(deng)諸多困難,高標(biao)準、高質(zhi)量推(tui)進工(gong)(gong)程(cheng)進度。特別(bie)是在收(shou)尾驗收(shou)中(zhong),他(ta)們嚴格自檢自查,查出并徹底整改問題2700余項,確(que)保(bao)了水(shui)(shui)(shui)汽項目的(de)高標(biao)準、高質(zhi)量竣(jun)工(gong)(gong)。

  公用供熱外管廊實現機械竣工

  5月31日(ri),該公(gong)司公(gong)用(yong)供熱外管(guan)(guan)廊順利通過驗收復查,實現機(ji)械竣工(gong)(gong)。該項目于2008年3月11日(ri)開工(gong)(gong),經過廣大建設(she)者14個月的艱苦奮戰,完(wan)(wan)成管(guan)(guan)樁施工(gong)(gong)632根(gen),澆筑混凝(ning)土1100立方(fang)米(mi),制作安裝鋼(gang)結構1700噸,鋪(pu)設(she)各類管(guan)(guan)線27條(tiao)約15000延長(chang)米(mi),完(wan)(wan)成保(bao)溫絕熱工(gong)(gong)程3200立方(fang)米(mi)。特別是攻(gong)克了冬(dong)季施工(gong)(gong)難題,保(bao)質保(bao)量(liang)保(bao)進度完(wan)(wan)成了1020米(mi)φ711高(gao)壓管(guan)(guan)線施工(gong)(gong),確保(bao)了供熱外管(guan)(guan)廊工(gong)(gong)程的高(gao)標準、高(gao)質量(liang)、高(gao)效率竣工(gong)(gong)。