文章來(lai)源:中國(guo)華電(dian)集團(tuan)公司 發布(bu)時間:2012-03-23
3月17日,華電(dian)寧夏靈(ling)武(wu)發電(dian)有(you)限公司二期工程#4機組鍋爐點(dian)火一次成(cheng)功,此次點(dian)火成(cheng)功為即將進(jin)行的鍋爐吹(chui)管工作打下了牢(lao)固的基(ji)礎。
#4機(ji)組(zu)進入(ru)安(an)裝調試高峰期(qi)(qi)以來,靈(ling)武公司將“創先爭優”融入(ru)工(gong)(gong)程(cheng)建(jian)(jian)設,開展(zhan)了“大(da)干60天,投產(chan)#4機(ji),為建(jian)(jian)黨90周年獻禮”活動,激發廣大(da)黨員(yuan)職工(gong)(gong)活力,團結(jie)各(ge)(ge)參(can)建(jian)(jian)單(dan)位克(ke)服重重困難確保機(ji)組(zu)早日高效投產(chan)。在(zai)進度(du)管理方面,該(gai)公司超前做好(hao)各(ge)(ge)項施工(gong)(gong)準備工(gong)(gong)作,進一步細化#4機(ji)組(zu)鍋爐點(dian)(dian)火前施工(gong)(gong)、調試計(ji)劃(hua),將計(ji)劃(hua)完成時(shi)間精(jing)確到(dao)小(xiao)時(shi)。同時(shi),嚴格(ge)控制計(ji)劃(hua)完成情(qing)況,不斷加大(da)設備催交力度(du),保證了現場(chang)的連續施工(gong)(gong)。為正確處理施工(gong)(gong)主(zhu)線(xian)與輔(fu)線(xian)的關系,在(zai)確保主(zhu)線(xian)工(gong)(gong)程(cheng)工(gong)(gong)期(qi)(qi)目(mu)標(biao)的同時(shi),扎實推(tui)進輔(fu)線(xian)工(gong)(gong)作的順利開展(zhan),并充分協調參(can)建(jian)(jian)各(ge)(ge)方人(ren)員(yuan),克(ke)服了施工(gong)(gong)場(chang)地緊張、寒冷季節施工(gong)(gong)難、施工(gong)(gong)人(ren)員(yuan)少等困難,為#4爐一次點(dian)(dian)火成功里程(cheng)碑節點(dian)(dian)的提前高質量完成提供了保證。
下一(yi)步,靈武公司(si)將繼續深化工程管理創新,精(jing)心(xin)施工、精(jing)心(xin)調試,確保(bao)#4機(ji)組投產(chan)各項(xiang)指標水平優于#3機(ji)組。