7月16日16時08分,隨著15號風機順利并網,福建大唐國際風電公司詔安梅嶺風電場工程24臺風機實現全部并網,提前15天完成工程節點任務。
大唐福建梅嶺工程項目是福建風電公司今年重要的一項在建工程,項目工程共安裝24臺風機,總裝機容量48兆瓦,預計年發電量將達到9633萬千瓦時。
為(wei)早日完成全(quan)場(chang)風機并網發(fa)電(dian)任(ren)務,大唐(tang)福建風電(dian)公司和風電(dian)場(chang)項(xiang)目(mu)(mu)部(bu)(bu)的(de)干部(bu)(bu)員工(gong)(gong)(gong),秉承“特別能(neng)(neng)吃苦、特別能(neng)(neng)戰斗、特別能(neng)(neng)奉獻”的(de)企業精(jing)神,團結一心(xin),攻(gong)堅克難(nan)。面對(dui)(dui)征地問題,奔走于政府(fu)、村鎮之間,做工(gong)(gong)(gong)作,講(jiang)政策;面對(dui)(dui)設(she)備(bei)安(an)(an)裝,組(zu)織施工(gong)(gong)(gong)單位每天提前開(kai)工(gong)(gong)(gong),加班加點進行風機吊裝;為(wei)保(bao)證安(an)(an)全(quan)生產,積(ji)極建立安(an)(an)全(quan)組(zu)織網絡,制(zhi)定安(an)(an)全(quan)管(guan)理(li)(li)規章制(zhi)度,劃分安(an)(an)全(quan)文明施工(gong)(gong)(gong)責任(ren)區,加強施工(gong)(gong)(gong)現場(chang)習慣(guan)性違章管(guan)理(li)(li),將(jiang)“安(an)(an)全(quan)第一、預防為(wei)主”理(li)(li)念落到實(shi)處,在整個工(gong)(gong)(gong)程建設(she)中,未出現人身、設(she)備(bei)傷害事(shi)件;同時,積(ji)極與施工(gong)(gong)(gong)單位進行項(xiang)目(mu)(mu)施工(gong)(gong)(gong)設(she)計優化,最終(zhong)確(que)保(bao)工(gong)(gong)(gong)程保(bao)質(zhi)、按期順利完成。