文章(zhang)來源(yuan):中(zhong)國(guo)冶金科工集(ji)團有(you)限公司(si) 發(fa)布時間:2013-08-13
8月10日上午10時18分,由中國中冶所屬中國華冶集團北票分公司承建的凌鋼保國鐵礦鐵蛋山礦區副井技改工程竣工投產,比合同工期提前143天,技改工程達產后年出礦量將由過去100萬噸/年增強到180萬噸/年。
該工(gong)(gong)(gong)程是凌(ling)鋼擴大(da)原(yuan)料產能(neng)的(de)重點項目(mu),施工(gong)(gong)(gong)難度(du)大(da),工(gong)(gong)(gong)程構成(cheng)(cheng)復雜,由(you)600多米深的(de)副(fu)井(jing)(jing)和(he)風井(jing)(jing)、600多米斜坡(po)道、14條75米天溜(liu)井(jing)(jing)、一條90多米的(de)電梯井(jing)(jing)、5800米巷道組(zu)成(cheng)(cheng)。尤其是由(you)-40水平斜坡(po)道向副(fu)井(jing)(jing)貫通的(de)1101米的(de)獨頭巷道,施工(gong)(gong)(gong)難度(du)極其艱(jian)苦。自2010年6月(yue)中(zhong)(zhong)國華冶集團北票分公司中(zhong)(zhong)標承建鐵蛋(dan)山礦(kuang)區技改(gai)工(gong)(gong)(gong)程后,精心(xin)組(zu)織(zhi),科學管(guan)理,創造出全國冶金(jin)礦(kuang)山豎(shu)井(jing)(jing)月(yue)成(cheng)(cheng)井(jing)(jing)205.6米的(de)新(xin)紀錄,成(cheng)(cheng)為同行業(ye)對標學習的(de)榜(bang)樣。整個工(gong)(gong)(gong)程僅(jin)用了26個月(yue),比合(he)同工(gong)(gong)(gong)期提前143天,經業(ye)主(zhu)和(he)工(gong)(gong)(gong)程監理驗收工(gong)(gong)(gong)程質量合(he)格率100%,優(you)良率達90%以上,安全無事故。