文章來源:中國(guo)核工業集團(tuan)公司 發布時間:2014-04-15
4月(yue)10日13時50分,中核(he)集團方家山核(he)電工(gong)程2號(hao)機組(zu)核(he)島6.6千伏(fu)首次受電考(kao)核(he)完(wan)成(cheng)。本次受電范圍包括7個中壓系統,各項指標符合設計要求,順利實(shi)現節點(dian)目標。
本次受(shou)(shou)電(dian)成功,標志著方家山核(he)電(dian)工程2號機組核(he)島6.6千(qian)伏已(yi)基本具備可用(yong)條(tiao)件(jian)。受(shou)(shou)電(dian)完成后(hou)(hou),上(shang)述系統將(jiang)移交調(diao)試(shi)隊(dui)完成最后(hou)(hou)調(diao)試(shi)工作,而后(hou)(hou)將(jiang)正(zheng)式帶(dai)電(dian)運行,為2號泵(beng)房進水創造條(tiao)件(jian)。
為(wei)實現受電(dian)(dian)節點目(mu)標,中國(guo)核電(dian)(dian)工(gong)(gong)(gong)(gong)程有(you)限公(gong)司方家山(shan)項(xiang)目(mu)部成(cheng)立了倒(dao)送電(dian)(dian)工(gong)(gong)(gong)(gong)作組(zu)(zu),包括安(an)全、技術、質(zhi)量(liang)、送電(dian)(dian)等4個工(gong)(gong)(gong)(gong)作小組(zu)(zu),明確了各小組(zu)(zu)的(de)工(gong)(gong)(gong)(gong)作職責和責任(ren)人,制定(ding)了倒(dao)送電(dian)(dian)的(de)審批和操作流程以及(ji)各種(zhong)應(ying)急預(yu)案。同時施工(gong)(gong)(gong)(gong)部根據1號(hao)機組(zu)(zu)的(de)經驗反饋,一(yi)方面(mian)協(xie)調土建施工(gong)(gong)(gong)(gong)單(dan)位完(wan)善房間(jian)內的(de)施工(gong)(gong)(gong)(gong)環境,另一(yi)方面(mian)協(xie)調安(an)裝單(dan)位加強成(cheng)品(pin)保(bao)(bao)護措(cuo)施,使(shi)受電(dian)(dian)設備安(an)裝后(hou)始終保(bao)(bao)持(chi)良好(hao)狀(zhuang)態,保(bao)(bao)證了受電(dian)(dian)的(de)成(cheng)功實施。