文章來(lai)源:國家電網公司 發布時間(jian):2014-01-07
2012年12月29日下午,為門頭溝石門營地區保障性住房提供電源的石門營新八區配電室完成最后的送電工作,標志著北京市2012年保障性住房配套電力設施建設工程全面完工。
據了解(jie),2012年北京市保障(zhang)性住(zhu)房竣工(gong)(gong)(gong)計劃共計80項,已(yi)全(quan)(quan)部按(an)時送(song)電(dian)(dian)(dian)。全(quan)(quan)年送(song)電(dian)(dian)(dian)戶數9萬戶,送(song)電(dian)(dian)(dian)容量22萬千(qian)伏安,新(xin)建21座開(kai)閉站、264座配電(dian)(dian)(dian)室,工(gong)(gong)(gong)程(cheng)量比2011年增長10%。北京市電(dian)(dian)(dian)力公(gong)司將保障(zhang)房用電(dian)(dian)(dian)報裝項目列入重(zhong)點工(gong)(gong)(gong)程(cheng),開(kai)辟綠(lv)色通(tong)道,采取(qu)倒(dao)排工(gong)(gong)(gong)期的(de)(de)形式,保證工(gong)(gong)(gong)程(cheng)實施進度(du)(du)。在對各(ge)項工(gong)(gong)(gong)作提(ti)出時限要求(qiu)的(de)(de)基礎上,壓縮各(ge)業務環節(jie)工(gong)(gong)(gong)作時限,統籌協調(diao)各(ge)相關業務環節(jie)的(de)(de)實施。建立(li)定(ding)點聯系制度(du)(du),主動走訪項目建設單位(wei),跟(gen)蹤掌握工(gong)(gong)(gong)程(cheng)進度(du)(du)等情(qing)況,及時協調(diao)處理(li)施工(gong)(gong)(gong)過程(cheng)中存在的(de)(de)問題,確保質量和進度(du)(du)。