國電懷安熱電公司1#機組順利完成168小時試運

文章來源(yuan):中國國電集團公司  發布時間:2008-12-24

  國電懷(huai)安(an)熱電有限公司1號機(ji)組于12月10日1時12分(fen)首次并網,12月13日5時至12月20日5時高標準完成168小時滿負荷試運。

  自2006年9月1日開工(gong)(gong)(gong)建設以來,公司(si)就圍繞工(gong)(gong)(gong)程(cheng)(cheng)建設這(zhe)一中(zhong)心任(ren)務(wu),和所有參建單(dan)位團結奮戰,無私奉獻、科(ke)學組織(zhi),精心指揮(hui),嚴格施工(gong)(gong)(gong),抓安全(quan),保(bao)質量,搶工(gong)(gong)(gong)期(qi),克服了建設場地狹小、工(gong)(gong)(gong)期(qi)緊、任(ren)務(wu)重、設備到(dao)貨晚、送出工(gong)(gong)(gong)程(cheng)(cheng)滯(zhi)后、寒(han)冷地區(qu)冬(dong)季施工(gong)(gong)(gong)難度大等重重困難,牢(lao)(lao)牢(lao)(lao)抓住“安全(quan)、質量、工(gong)(gong)(gong)期(qi)、造價”四控制主線,努(nu)力提(ti)高(gao)工(gong)(gong)(gong)程(cheng)(cheng)管(guan)理水(shui)平和安裝工(gong)(gong)(gong)藝質量,保(bao)證了工(gong)(gong)(gong)程(cheng)(cheng)建設快速、穩步推進。

  1號機組168小時(shi)試(shi)運期間,各項(xiang)技術指標均(jun)達到(dao)了同類機組先進(jin)水(shui)平(ping)(ping),連(lian)續平(ping)(ping)均(jun)負荷率達100.1%,熱(re)控自(zi)動和保護(hu)裝置投入率達到(dao)100%。

  國電(dian)懷(huai)安熱電(dian)項目是2006年(nian)4月(yue)18日國家(jia)發改委(wei)核準批復建(jian)(jian)設2臺(tai)330MW國產亞臨界(jie)燃(ran)煤供熱空冷發電(dian)機組,位于河北省懷(huai)安縣, 2006年(nian)9月(yue)1日正式開(kai)工建(jian)(jian)設。分別由中國國電(dian)集團公司(si)、河北華峰投資(zi)有限公司(si)、衡水衡冠實業有限責(ze)任(ren)公司(si)按照(zhao)5.5:3.5:1的比例(li)共(gong)同(tong)投資(zi)建(jian)(jian)設。懷(huai)安熱電(dian)項目實現了控制系(xi)統一(yi)體化(hua)(hua),即:主機、輔(fu)機、網控、空冷、脫硫、輸煤、化(hua)(hua)水等(deng)系(xi)統全部納(na)入(ru)DCS控制系(xi)統。廠區布(bu)置緊(jin)湊,大量采用了新(xin)型節能技術。

  1#機組168小時滿負荷試運的完成,標志著國電懷安熱電有限公司首臺330MW機組順利轉入商業運營,為中國國電集團公司“做實、做新、做大、做強”的戰略方針獻上了一份珍貴的禮物。