文(wen)章來(lai)源:中國(guo)冶金科工集團(tuan)公司 發布(bu)時間:2009-01-03
近日,由中冶(ye)天(tian)工(gong)建(jian)設有(you)限(xian)公司承(cheng)建(jian)的北京天(tian)堂河污(wu)水處理廠施工(gong)現(xian)場禮炮(pao)轟鳴、人頭攢動,伴隨澆(jiao)注混(hun)凝土(tu)的最(zui)后(hou)一(yi)聲口哨響落,主(zhu)體工(gong)程提前10天(tian)順利實(shi)現(xian)封頂。它的建(jian)成,為(wei)企業在污(wu)水處理工(gong)程領域中又贏得了一(yi)項(xiang)新的業績。
天堂(tang)河污(wu)(wu)水處理廠(chang)(chang)位于北京市大興區新城(cheng)南(nan)側,規(gui)劃占地(di)面(mian)積10.4公頃,其中用(yong)地(di)面(mian)積為(wei)(wei)(wei)(wei)(wei)5.0公頃,代征地(di)面(mian)積5.4公頃,是全國第(di)一(yi)(yi)個(ge)地(di)下(xia)(xia)式覆土綠化(hua)污(wu)(wu)水處理廠(chang)(chang),其環保和(he)全封(feng)閉的(de)理念迎(ying)合(he)(he)了(le)規(gui)劃后(hou)長期(qi)發(fa)展的(de)趨勢。廠(chang)(chang)區邊界分(fen)別為(wei)(wei)(wei)(wei)(wei):北邊緊鄰魏永(yong)路(lu),西側與大臧村相連(lian),東側為(wei)(wei)(wei)(wei)(wei)天堂(tang)河,南(nan)側為(wei)(wei)(wei)(wei)(wei)建(jian)(jian)(jian)設基本農田;工(gong)(gong)程總規(gui)模(mo)為(wei)(wei)(wei)(wei)(wei)8萬(wan)立(li)方米/日,其中一(yi)(yi)期(qi)工(gong)(gong)程建(jian)(jian)(jian)設規(gui)模(mo)為(wei)(wei)(wei)(wei)(wei)日處理污(wu)(wu)水量(liang)4萬(wan)立(li)方米,二期(qi)工(gong)(gong)程建(jian)(jian)(jian)設規(gui)模(mo)為(wei)(wei)(wei)(wei)(wei)日處理污(wu)(wu)水量(liang)4萬(wan)立(li)方米;主要建(jian)(jian)(jian)筑物名稱(cheng)有粗(cu)格柵(zha)(zha)、細格柵(zha)(zha)、污(wu)(wu)水提(ti)升泵房、旋(xuan)流沉砂池、綜合(he)(he)樓、變配電間、生化(hua)池、二沉池、污(wu)(wu)泥(ni)貯(zhu)池、污(wu)(wu)泥(ni)脫水間、紫外消(xiao)毒渠、除臭濾池等。在(zai)建(jian)(jian)(jian)設單位和(he)我方的(de)合(he)(he)同中約定,一(yi)(yi)期(qi)工(gong)(gong)程分(fen)為(wei)(wei)(wei)(wei)(wei)二個(ge)階(jie)段進行,第(di)一(yi)(yi)階(jie)段目標(biao)為(wei)(wei)(wei)(wei)(wei)2007年12月31日前主體工(gong)(gong)程完(wan)畢,第(di)二階(jie)段目標(biao)為(wei)(wei)(wei)(wei)(wei)2008年6月30日前設備安裝、調試完(wan)畢,目前第(di)一(yi)(yi)階(jie)段目標(biao)已提(ti)前10天完(wan)成,在(zai)保證進度的(de)前提(ti)下(xia)(xia)很好履約了(le)合(he)(he)同。
截至今年年底,項目部累計完成施工產值3600萬元,主體結構全部完成,其中混凝土澆筑28000立方米、模板用量79000平方米,鋼筋綁扎用量為3400噸。腳手架管120000米,扣件25萬個,施工人員最高峰為300人,人均產值為90000元/人,圓滿完成了經營指標。項目部全體員工將用高標準的要求鑄造高品質工程,為企業創造良好的信譽平臺而努力。