安徽電力搶修重建±500千伏江城線取得階段性進展

文章來源:國家(jia)電(dian)網公(gong)司  發布時(shi)間:2009-02-27

  2月25日,由安徽省電(dian)力公(gong)司(si)負責(ze)搶修的(de)±500千伏江城線廣(guang)東韶關段1648~1654號區段的(de)導(dao)線展放完畢,提前兩(liang)天(tian)完成(cheng)了預定目(mu)標(biao)。

  當天(tian)施(shi)(shi)工進展(zhan)(zhan)(zhan)迅速。從早晨七(qi)點鐘開始,施(shi)(shi)工人(ren)員在蒙(meng)蒙(meng)細雨中完成(cheng)了本區(qu)段(duan)的(de)地(di)線(xian)(xian)和(he)光纜(lan)展(zhan)(zhan)(zhan)放(fang)(fang),地(di)線(xian)(xian)、光纜(lan)緊掛(gua)作業和(he)導線(xian)(xian)展(zhan)(zhan)(zhan)放(fang)(fang)施(shi)(shi)工同時進行(xing)。經過一(yi)天(tian)的(de)艱苦奮戰,該區(qu)段(duan)導線(xian)(xian)展(zhan)(zhan)(zhan)放(fang)(fang)、緊掛(gua)施(shi)(shi)工全(quan)部完成(cheng)。目前(qian)剩余(yu)搶修工作量包括另(ling)一(yi)個區(qu)段(duan)的(de)導線(xian)(xian)、地(di)線(xian)(xian)和(he)光纜(lan)的(de)展(zhan)(zhan)(zhan)放(fang)(fang),以及近20公里的(de)導線(xian)(xian)修復和(he)附件安(an)裝等工作。預計(ji)全(quan)部導地(di)線(xian)(xian)、光纜(lan)的(de)展(zhan)(zhan)(zhan)放(fang)(fang)施(shi)(shi)工將于(yu)2月27日全(quan)面(mian)完成(cheng)。

  為盡快(kuai)修復重建在雪災中(zhong)受損的(de)(de)±500千伏江城線路,圓滿完成國家電(dian)網(wang)公(gong)司(si)(si)交付(fu)的(de)(de)搶修任務,安徽省電(dian)力(li)(li)公(gong)司(si)(si)克服(fu)任務艱巨、條件艱苦、施(shi)工(gong)(gong)(gong)環境惡(e)劣等困難,周密(mi)部署,合理(li)調(diao)配(pei),充分(fen)(fen)投(tou)(tou)入(ru)人力(li)(li)、物力(li)(li)。自2月(yue)9日搶修工(gong)(gong)(gong)作開始,相(xiang)繼投(tou)(tou)入(ru)44個施(shi)工(gong)(gong)(gong)隊、施(shi)工(gong)(gong)(gong)人員1600名,車輛(liang)68臺,拆塔、立塔工(gong)(gong)(gong)器具16套,牽張機5套,調(diao)用(yong)馬(ma)幫的(de)(de)運輸戰馬(ma)80匹(pi)。通過不斷優化(hua)搶修方(fang)案(an),倒排工(gong)(gong)(gong)期(qi)精(jing)確到(dao)每(mei)個半天,統籌安排,周密(mi)部署,實現(xian)施(shi)工(gong)(gong)(gong)人員和(he)物資(zi)的(de)(de)“零缺位、零周轉(zhuan)”,工(gong)(gong)(gong)序銜接(jie)和(he)交叉作業做到(dao)“無縫對(dui)接(jie)”。施(shi)工(gong)(gong)(gong)過程中(zhong)全(quan)面落(luo)實國家電(dian)網(wang)公(gong)司(si)(si)《抗冰(bing)搶修施(shi)工(gong)(gong)(gong)安全(quan)要點》和(he)《關于加(jia)強(qiang)搶險工(gong)(gong)(gong)程質量管(guan)理(li)的(de)(de)通知》。加(jia)強(qiang)施(shi)工(gong)(gong)(gong)組(zu)織管(guan)理(li),細化(hua)工(gong)(gong)(gong)作職責和(he)分(fen)(fen)工(gong)(gong)(gong),確保搶修施(shi)工(gong)(gong)(gong)管(guan)理(li)安全(quan)有(you)序。

  截至2月(yue)25日(ri)晚間,安徽省電力(li)公(gong)司(si)已(yi)完成16基(ji)(ji)拆塔、12基(ji)(ji)鐵塔組(zu)立(li)、一(yi)個區段的導(dao)地線、光纜展放和24公(gong)里的導(dao)線修(xiu)(xiu)復施工,整體(ti)工作量完成已(yi)超出三分之(zhi)二。目(mu)前搶修(xiu)(xiu)施工正在按(an)計劃緊張有序進行。