文章來源(yuan):中(zhong)國葛(ge)洲壩集團公司(si) 發(fa)布時(shi)間:2009-09-24
9月18日下(xia)午,向家壩(ba)水(shui)電站沖砂(sha)孔壩(ba)段(duan)丙塊混凝(ning)土順利澆筑,標(biao)志(zhi)著電站左(zuo)岸大壩(ba)6個導(dao)流(liu)底孔全部達到進水(shui)口底板高程(cheng)(cheng),為(wei)向家壩(ba)工程(cheng)(cheng)年(nian)底截流(liu)目標(biao)的(de)實現打(da)下(xia)了良(liang)好的(de)基礎。
據了解,這6個(ge)導(dao)流(liu)(liu)底孔(kong)分別布置在向家壩(ba)水電站左非壩(ba)段(duan)及沖砂孔(kong)壩(ba)段(duan)內,每(mei)個(ge)導(dao)流(liu)(liu)底孔(kong)寬10米,高14米。其(qi)中1號(hao)(hao)至4號(hao)(hao)導(dao)流(liu)(liu)底孔(kong)孔(kong)長152.5米,5號(hao)(hao)和(he)6號(hao)(hao)導(dao)流(liu)(liu)底孔(kong)孔(kong)長220.45米。工(gong)(gong)程量(liang)大(da),結構(gou)復雜,質量(liang)要求高,施(shi)工(gong)(gong)難度大(da)。承擔施(shi)工(gong)(gong)的葛洲(zhou)壩(ba)集團向家壩(ba)施(shi)工(gong)(gong)局(ju)混凝土項目部,科(ke)學配(pei)置資源,認真編(bian)制施(shi)工(gong)(gong)技術(shu)指導(dao)書(shu),組織施(shi)工(gong)(gong)人員進(jin)行嚴格的培訓,確(que)保了工(gong)(gong)程順利推進(jin)。