文章來源:國(guo)家電網公司 發布(bu)時間:2009-09-25
9月22日,1000千伏特高壓(ya)交流(liu)試驗示范工程線路(lu)山西段(duan)的竣工預驗收工作圓滿完成。特高壓(ya)線路(lu)工程山西段(duan)為全線第1~3標段(duan),總長107.484千米,鐵塔212基,途(tu)經(jing)長治市長子縣,晉城市沁水縣、澤州(zhou)縣。
國網交流工(gong)(gong)程(cheng)(cheng)建設有(you)(you)限公司專門(men)編制(zhi)了《特高壓交流試驗(yan)(yan)示(shi)范工(gong)(gong)程(cheng)(cheng)線路(lu)工(gong)(gong)程(cheng)(cheng)竣工(gong)(gong)驗(yan)(yan)收辦法》。驗(yan)(yan)收單位按工(gong)(gong)程(cheng)(cheng)投運前的全面檢查(cha)標準,對鐵(tie)塔和(he)(he)導(dao)線工(gong)(gong)程(cheng)(cheng)進(jin)行驗(yan)(yan)收,另有(you)(you)兩個(ge)小組(zu)進(jin)行測量和(he)(he)地面檢查(cha)驗(yan)(yan)收。預驗(yan)(yan)收的提早完(wan)成,為(wei)竣工(gong)(gong)驗(yan)(yan)收創造了良好的條件。