文(wen)章來源:中國核工業(ye)集團(tuan)公(gong)司 發布時間:2009-10-16
10月8日,三門核(he)電工(gong)(gong)(gong)程(cheng)1號核(he)島底板防水(shui)工(gong)(gong)(gong)程(cheng)順利實(shi)施完(wan)成,這標志(zhi)著三門核(he)電主(zhu)工(gong)(gong)(gong)程(cheng)項目在(zai)繼下墊層混(hun)凝土工(gong)(gong)(gong)程(cheng)完(wan)成后(hou),向澆(jiao)灌(guan)第(di)一罐混(hun)凝土的(de)目標又前進了一步。
三門核電(dian)核島底板防水(shui)工(gong)(gong)程涉及(ji)新材料和新工(gong)(gong)藝的應用。三門核電(dian)有限(xian)公司工(gong)(gong)程管理部門與現場各級承包(bao)商一起,克服各種施工(gong)(gong)問(wen)題(ti)和設計問(wen)題(ti),于(yu)10月4日開始敷設核島底板防水(shui)卷材,10月8日完成了全部施工(gong)(gong)。