文章來源:中國葛洲壩集(ji)團公(gong)司 發布時間:2009-11-05
十一月初,葛洲壩集團三峽指揮部廠房項目部再傳捷報,在確保質量、安全“雙零”目標的前提下,該項目部承擔施工的三峽地下電站廠房項目施工進展迅速,先后創下了十月月澆筑混凝土突破19000立方米,混凝土襯砌班產584立方米、日產1314立方米的好成績。
10月份是水電施(shi)工(gong)(gong)(gong)黃(huang)金(jin)季(ji)節(jie),為(wei)確(que)保節(jie)點控制工(gong)(gong)(gong)期,滿足三(san)(san)峽地下(xia)電站澆(jiao)筑形象進度要(yao)求,葛洲(zhou)壩人細化施(shi)工(gong)(gong)(gong)計劃,合理配置資源(yuan),嚴格執行(xing)“三(san)(san)檢制”,不斷優化施(shi)工(gong)(gong)(gong)方案,掀起了四季(ji)度施(shi)工(gong)(gong)(gong)高(gao)潮(chao)。目(mu)前,葛洲(zhou)壩集團承擔施(shi)工(gong)(gong)(gong)的三(san)(san)峽地下(xia)電站主廠房29號機、30號機已(yi)澆(jiao)至42.5米(mi)高(gao)程,具(ju)備向45米(mi)高(gao)程以上(shang)標(biao)段(duan)交(jiao)面條件;承擔施(shi)工(gong)(gong)(gong)的地下(xia)電站尾水擴散段(duan)、母(mu)線廊道(dao)等項目(mu)已(yi)進入混凝(ning)土澆(jiao)筑階段(duan),各項施(shi)工(gong)(gong)(gong)正有序進行(xing)。