中國通號集團堅持“總體布局、分段突擊、均衡生產、確保重點、快速推進”的原則,結合武廣客運專線工程實際優化組織、規范管理,科學施工,緊張有序地推進工作,目前,在參建員工的共同努力下,武廣客專綜合試驗段通信信號工程進度按照業主計劃實施,完成基本功能的聯調聯試。
正線(xian)全(quan)長968.57公里有18個車站的武廣客運專線(xian)工(gong)(gong)程(cheng),預(yu)計于2009年8月31日全(quan)線(xian)竣工(gong)(gong)。面對緊張的工(gong)(gong)程(cheng)形勢(shi),中國通號(hao)集(ji)團根(gen)據(ju)工(gong)(gong)程(cheng)和綜(zong)合(he)(he)試(shi)驗(yan)段的現(xian)狀(zhuang),與(yu)設計、建設單(dan)位、地方政府(fu)聯系溝(gou)通,營造(zao)外部和諧施(shi)工(gong)(gong)環境;與(yu)站前(qian)單(dan)位聯系溝(gou)通,見縫插針交叉(cha)施(shi)工(gong)(gong);依據(ju)現(xian)有圖(tu)紙(zhi),進(jin)行估(gu)料,及時做好物資設備儲備與(yu)供應;科學安(an)排施(shi)工(gong)(gong)資源合(he)(he)理控制各道工(gong)(gong)序,實現(xian)均(jun)衡(heng)生產,克服(fu)站前(qian)施(shi)工(gong)(gong)的不利(li)影響(xiang),尤其是(shi)他們根(gen)據(ju)武廣客運專線(xian)綜(zong)合(he)(he)試(shi)驗(yan)段建設情況建立(li)的信號(hao)工(gong)(gong)程(cheng)仿真線(xian)路(lu)試(shi)驗(yan)基地,為員工(gong)(gong)掌握相(xiang)關(guan)施(shi)工(gong)(gong)工(gong)(gong)藝、安(an)裝方法、設備性能、安(an)全(quan)防范要(yao)求,在(zai)工(gong)(gong)程(cheng)進(jin)入實施(shi)階段快(kuai)速(su)準確按節點目標完成施(shi)工(gong)(gong)提供了保(bao)障。