文章來(lai)源:國(guo)家電(dian)網(wang)公司 發布(bu)時間(jian):2011-01-21
為優(you)化三峽電(dian)力外送(song),提高(gao)500千伏(fu)輸電(dian)線(xian)路防冰(bing)防雷擊能力,近日,國(guo)家電(dian)網湖北超(chao)(chao)高(gao)壓(ya)輸變電(dian)公司(si)積極開展三峽地區(qu)15條500千伏(fu)超(chao)(chao)高(gao)壓(ya)輸電(dian)線(xian)路防雷防冰(bing)改造(zao)工作。
按照國網公(gong)司(si)要求,該公(gong)司(si)編(bian)寫了(le)詳盡的(de)施工(gong)(gong)(gong)方案,組織生產(chan)廠家代表(biao)圖文并茂地介紹(shao)了(le)避(bi)雷(lei)器安(an)裝的(de)相(xiang)關注意事項,認(ren)真(zhen)解答(da)施工(gong)(gong)(gong)方提出的(de)危險點(dian)(dian)和技術(shu)難(nan)點(dian)(dian)及相(xiang)關流(liu)程(cheng),并設立(li)專門材料站。改造過程(cheng)中,該公(gong)司(si)積極做好各種安(an)全措施,認(ren)真(zhen)履行工(gong)(gong)(gong)作職責,加(jia)大施工(gong)(gong)(gong)現(xian)(xian)場安(an)全監察力度,對(dui)安(an)全隱患做到(dao)及時發現(xian)(xian)及時消(xiao)除,協調監護(hu)人員和施工(gong)(gong)(gong)人員間技術(shu)交流(liu),避(bi)免(mian)出現(xian)(xian)重復和返工(gong)(gong)(gong)現(xian)(xian)象,有效地保證了(le)工(gong)(gong)(gong)作的(de)順(shun)利進行。
預計此次防雷(lei)(lei)(lei)冰(bing)改造工作(zuo)將于春節前完成7條線路(lu)共128基(ji)(ji)桿塔(ta)(ta)避(bi)(bi)雷(lei)(lei)(lei)器安(an)裝(zhuang),432基(ji)(ji)桿塔(ta)(ta)可控(kong)避(bi)(bi)雷(lei)(lei)(lei)針(zhen)安(an)裝(zhuang)、213基(ji)(ji)桿塔(ta)(ta)防繞(rao)擊避(bi)(bi)雷(lei)(lei)(lei)針(zhen)安(an)裝(zhuang)和(he)675基(ji)(ji)桿塔(ta)(ta)地(di)線支(zhi)架更換(huan)檢(jian)修任務。1月5日—9日,該公(gong)司已(yi)完成了(le) 500千伏峽江(jiang)一回檢(jian)修技改工作(zuo),安(an)裝(zhuang)避(bi)(bi)雷(lei)(lei)(lei)器14只共7基(ji)(ji)塔(ta)(ta),可控(kong)放(fang)電避(bi)(bi)雷(lei)(lei)(lei)針(zhen)38基(ji)(ji)塔(ta)(ta),防繞(rao)擊避(bi)(bi)雷(lei)(lei)(lei)針(zhen)2基(ji)(ji)塔(ta)(ta)。
據悉,此(ci)次大規模地開展500千伏輸(shu)電線路避雷器安裝(zhuang)和地線支架改造等線路防雷防冰工作,在國內(nei)尚屬(shu)于首(shou)次。此(ci)次防雷防冰技(ji)改項目的(de)實施(shi),將有力(li)保障三峽(xia)電力(li)外(wai)送通道順(shun)暢(chang),真正起(qi)到“構造堅強電網,暢(chang)通電網主動脈”的(de)作用。