文章來源(yuan):中國(guo)能(neng)源(yuan)建設(she)集團有限公(gong)司 發布時間(jian):2019-03-07
近(jin)日,由中國能(neng)建中電(dian)(dian)(dian)工程華東院(yuan)承擔常規(gui)島(dao)設計(ji)的(de)“華龍(long)一號”全球首堆示(shi)范工程福清(qing)核電(dian)(dian)(dian)5、6號機組(zu)220千伏倒(dao)送電(dian)(dian)(dian)圓滿完(wan)成,為機組(zu)后續安(an)裝(zhuang)、調試等工作創造了有利(li)條(tiao)件。
華東院秉承“精心設(she)計、優質服務”的理念,承擔了與220千(qian)伏倒送電(dian)(dian)相關(guan)的220千(qian)伏開關(guan)站(TD)、輔(fu)助變壓器區域(yu)及公用6.6千(qian)伏配電(dian)(dian)間(jian)(JX)、220千(qian)伏繼電(dian)(dian)器室(TC)內的系統以(yi)及相關(guan)的土建、建筑、暖通、消防、繼電(dian)(dian)保(bao)護、遠動和(he)通信(xin)等(deng)設(she)計內容。
本(ben)次220千(qian)伏(fu)(fu)倒(dao)(dao)(dao)送(song)(song)電(dian)(dian)工(gong)(gong)(gong)程建安工(gong)(gong)(gong)作共(gong)歷時14個月(yue)。早(zao)在2016年(nian)10月(yue),華東院福清核(he)電(dian)(dian)5、6號機組工(gong)(gong)(gong)程組為(wei)保證本(ben)次倒(dao)(dao)(dao)送(song)(song)電(dian)(dian)順利通過,制(zhi)定了詳細的220千(qian)伏(fu)(fu)倒(dao)(dao)(dao)送(song)(song)電(dian)(dian)相(xiang)關圖(tu)紙(zhi)出(chu)(chu)版(ban)(ban)計劃(hua),最終所有圖(tu)紙(zhi)均按(an)時或提前出(chu)(chu)版(ban)(ban),為(wei)此次220千(qian)伏(fu)(fu)倒(dao)(dao)(dao)送(song)(song)電(dian)(dian)的一次成功打下了良(liang)好的基礎。2018年(nian)春節前后,工(gong)(gong)(gong)程組電(dian)(dian)氣主設和(he)現場(chang)工(gong)(gong)(gong)代加班(ban)加點處理(li)現場(chang)提出(chu)(chu)的相(xiang)關技(ji)術問(wen)題,為(wei)確保220千(qian)伏(fu)(fu)倒(dao)(dao)(dao)送(song)(song)電(dian)(dian)的按(an)時完成貢獻了重要的力量(liang)。
此次倒送電成(cheng)功(gong)后(hou),220千伏(fu)輔助電源即為(wei)可用,為(wei)后(hou)續的除鹽水生產(chan)廠房(fang)(fang)制水、主控室可用、泵(beng)房(fang)(fang)進水、主泵(beng)組裝(zhuang)及試車等諸多工程節點(dian)提(ti)供(gong)了電源保(bao)證(zheng),為(wei)“華龍一號(hao)”全球首堆示范工程的順利建設奠(dian)定了堅實基礎(chu)。
【責任編輯:駱秧(yang)秧(yang)】